Issue - meetings

Ysgol Glanrafon, Mold - Capital Investment Project

Meeting: 20/10/2020 - Cabinet (Item 34)

Ysgol Glanrafon, Mold - Capital Investment Project

Additional documents:

Decision:

As detailed in the recommendation.

Minutes:

Councillor Roberts introduced the report which sought approval to enter into a contract for the construction phase of the capital improvement project at Ysgol Glanrafon, Mold.

 

            In response to comments from Councillor Thomas on car parking, the Chief Officer (Education and Youth) confirmed that work was ongoing on car park issues.

 

RESOLVED:

 

That entering into a contract for the construction phase of the capital investment project at Ysgol Glanrafon, Mold, be approved.