Issue - meetings

Maes Gwern Contractual Arrangements

Meeting: 17/11/2021 - Governance and Audit Committee (Item 44)

Maes Gwern Contractual Arrangements

Additional documents:

Decision:

That the report be accepted.

Minutes:

The Chief Officer (Governance) introduced the report on the Internal Audit review of Maes Gwern contractual arrangements and detailed background information.

 

Whilst the Senior Auditor provided information on the key considerations and findings which had been discussed with relevant officers, the newly appointed Housing Strategy & Development Manager shared an update on progress with actions to address risks identified.

 

Sally Ellis said that the report demonstrated good use of the Internal Audit service and officers confirmed that action implementation would be reviewed at a later stage.  In response to questions from Allan Rainford, officers gave assurance on the strengthening of monitoring arrangements.

 

The recommendation was moved and seconded by Councillors Geoff Collett and Arnold Woolley.

 

RESOLVED:

 

That the report be accepted.