Decision details

Contract Procurement Report for Connah's Quay High School

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the contract procurement for Connah's Quay High School.

Decisions:

Councillor Roberts introduced the Contract Procurement Report for Connah’s Quay High School which sought approval to contract with Kier Construction for the Capital investment project at Connah’s Quay High School.

 

RESOLVED:

 

That it be approved that the Council legally contract with Kier Construction to enable commencement for the construction of the capital improvement project at Connah’s Quay High School.

Report author: Damian Hughes

Publication date: 25/10/2017

Date of decision: 24/10/2017

Decided at meeting: 24/10/2017 - Cabinet

Effective from: 02/11/2017

  • Restricted enclosure  View reasons restricted
  •