Strategic Housing and Regeneration Programme (SHARP)

Decision Maker: Community and Enterprise Overview & Scrutiny Committee

Decision status: Recommendations Approved

Is Allweddol decision?: No

Is subject to call in?: No

Purpose:

To review progress on the Strategic Housing and Regeneration Project (SHARP)

Decision:

(a)       That the Committee support the development of 40 new Council homes on the 5 identified sites in Mold, Leeswood and Connah’s Quay at a projected total cost of £6,376,931M; and

 

(b)       That the Committee support the use of prudential borrowing to the value of £6,376,931M (subject to final approval and verification) to fund the proposed development of 40 new Council homes.

 

Report author: Melville Evans

Publication date: 13/07/2016

Date of decision: 13/07/2016

Decided at meeting: 13/07/2016 - Community and Enterprise Overview & Scrutiny Committee