Decision details

21st Century Schools Programme - Connah's Quay High School Project - Proposed Contract Variation

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Allweddol decision?: Yes

Is subject to call in?: Yes

Purpose:

To consider accelerating Phase 2 of Connah’s Quay High School investment scheme using Band B funding and a contract variation to enable project efficiencies of circa £220K.

Decisions:

Having earlier declared personal and prejudicial interests, Councillors Attridge and Jones left the room for this item.

 

                        Councillor Roberts introduced the 21st Century Schools Programme – Connah’s Quay High School project – Proposed Contract Variation report which sought approval to commission Kier Construction for stage one of a two stage Design and Build Contract for Phase 2 of the Capital improvement project at Connah’s Quay High School.

 

                        The proposed project would require successful submission of a Business Justification Case (BJC) to Welsh Government (WG) as it fell below the monetary value to trigger a Full Business Case (FBC).

 

RESOLVED:

 

That Cabinet support and approve entering into stage one of a two stage Design and Build contract with Kier Construction for Phase 2 of the build programme. Stage one will enable the detailed design work and cost certainty to be undertaken concurrently with the current contractor/team whilst the Phase 1 construction work is on site.

Report author: Neal Cockerton (old)

Publication date: 23/05/2018

Date of decision: 22/05/2018

Decided at meeting: 22/05/2018 - Cabinet

Effective from: 01/06/2018

Accompanying Documents:

  • 21st Century Schools Programme - Connah's Quay High School Project - Proposed Contract Variation