Decision details
21st Century Schools Programme - Connah's Quay High School Project - Proposed Contract Variation
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Allweddol decision?: Yes
Is subject to call in?: Yes
Purpose:
To consider accelerating Phase 2 of
Connah’s Quay High School investment scheme using Band B
funding and a contract variation to enable project efficiencies of
circa £220K.
Decisions:
Having earlier declared personal and prejudicial interests, Councillors Attridge and Jones left the room for this item.
Councillor Roberts introduced the 21st Century Schools Programme – Connah’s Quay High School project – Proposed Contract Variation report which sought approval to commission Kier Construction for stage one of a two stage Design and Build Contract for Phase 2 of the Capital improvement project at Connah’s Quay High School.
The proposed project would require successful submission of a Business Justification Case (BJC) to Welsh Government (WG) as it fell below the monetary value to trigger a Full Business Case (FBC).
RESOLVED:
That Cabinet support and approve entering into stage one of a two stage Design and Build contract with Kier Construction for Phase 2 of the build programme. Stage one will enable the detailed design work and cost certainty to be undertaken concurrently with the current contractor/team whilst the Phase 1 construction work is on site.
Report author: Neal Cockerton (old)
Publication date: 23/05/2018
Date of decision: 22/05/2018
Decided at meeting: 22/05/2018 - Cabinet
Effective from: 01/06/2018