Year End Improvement Plan Monitoring Report (2014/15)
Meeting: 16/06/2015 - Cabinet (Item 17)
17 Year End Improvement Plan Monitoring Report (2014/15). PDF 95 KB
Additional documents:
Decision:
As detailed in the recommendations.
Minutes:
The Chief Executive introduced the Year End Improvement Plan monitoring reports for the period 1 April 2014 to 31 March 2015.
An overall assessment was provided in the table in the report which was based on the detailed reports.
RESOLVED:
(a) That Cabinet Members note the sufficiency of actions taken to manage delivery of the Improvement Priority impacts; and
(b) That the following be noted:
· The levels of progress and confidence in the achievement of key activities which seek to deliver the impacts of the Improvement Plan;
· The levels of performance against Improvement Plan measures for year end; and
· The current (net) risk levels and targeted risk levels for the risks identified in the Improvement Plan and the arrangements to control them