Revenue Budget Monitoring 2015/16 (Month 12)

Meeting: 21/06/2016 - Cabinet (Item 24)

24 REVENUE BUDGET MONITORING 2015/16 (MONTH 12) pdf icon PDF 97 KB

Additional documents:

Decision:

As detailed in the recommendations.

Minutes:

The Corporate Finance Manager introduced the Revenue Budget Monitoring 2015/16 (Month 12) report which provided details on the latest revenue budget monitoring position for 2015/16 for the Council Fund and the Housing Revenue Account and reported that no specific issues had been raised when considered at the recent Corporate Resources Overview and Scrutiny Committee meeting.  The position was based on actual income and expenditure as at Month 11 and projected to the year-end.  Work was underway to close the 2015/16 accounts and the Final Outturn would be reported to Cabinet in July 2016.  The projected year-end position was as follows:

 

                        Council Fund

 

·         Net in year expenditure forecast to be £1.372m lower than budget

·         Projected contingency reserve balance at 31 March 2016 of £4.528m

 

Housing Revenue Account

 

·         Net in year expenditure forecast to be £0.093m lower than budget

·         Projected closing balance as at 31 March 2016 of £1.330m

 

The report provided details on significant budget movements between original and revised budget, the programme of efficiencies, inflation, un-earmaked reserves and earmarked reserves.

 

Various requests to carry forward funding into 2016/17 had been made, details of which were contained in appendix 6 to the report.

 

RESOLVED:

 

(a)       That the overall report and the projected Council Fund Contingency Sum as at 31st March 2016 be noted;

 

(b)       That the projected final level of balances on the Housing Revenue Account be noted; and

 

(c)        That the carry forward requests be agreed.