Capital Programme 2015/16 (Month 9)
Meeting: 22/03/2016 - Cabinet (Item 160)
160 Capital Programme 2015/16 (Month 9) PDF 119 KB
Additional documents:
- Enc. 1 for Capital Programme 2015/16 (Month 9), item 160 PDF 59 KB
- Enc. 2 for Capital Programme 2015/16 (Month 9), item 160 PDF 108 KB
Decision:
As detailed in the recommendations.
Minutes:
The Corporate Finance Manager introduced the Capital Programme Monitoring 2015/16 (Month 9) report, explaining that the Capital Programme had decreased by £3.320m in the period due to the impact of the following:
· Reduction in year to the 21st Century Schools Programme (£5.724m) and Wales Housing Quality Standard (WHQS) Improvements (£0.152m);
· Pre-approved Rollover into 2016/17 (£0.435m); and
· Other Aggregate Decreases (£0.052m).
Offset by:
· Additional Welsh Government (WG) Vibrant and Viable Places (VVP) grant (£1.367m); Introduction of European Regional Development Fund (ERDF) funding for Town Centre Regeneration (£0.561m);
· Additional Funding for Waste Services (£0.358m);
· Additional grant/contributions for Private Sector Renewal (£0.279m);
· Introduction of funding for play areas (£0.220m); and
· Other Aggregate Increases (£0.256m).
Resources available for funding future capital expenditure was c£2.986m.
As at Month 9, Early Identified Rollover (EIR) had been identified which reflected reviewed spending plans across all programme areas; those committed amounts had been identified as required to meet the cost of programme works in 2016/17.
Two pressure areas totalling £0.088m had been identified within the Streetscene and Transportation portfolio which were:
1. Overspend on remediation works at Standard Landfill site due to the presence of asbestos (£0.035m); and
2. Higher than expected contract price for the Queensferry roundabout improvement works (£0.053m)
RESOLVED:
(a) That the report be approved;
(b) That the rollover adjustments be approved; and
(c) That the request for additional resources be approved.