Capital Programme 2017/18 (Month 6)
Meeting: 21/11/2017 - Cabinet (Item 90)
90 Capital Programme 2017/18 (Month 6) PDF 116 KB
Additional documents:
- Enc. 1 for Capital Programme 2017/18 (Month 6), item 90 PDF 59 KB
- Enc. 2 for Capital Programme 2017/18 (Month 6), item 90 PDF 106 KB
Decision:
As detailed in the recommendations.
Minutes:
The Corporate Finance Manager introduced the Capital Programme Monitoring 2017/18 (Month 6) report which summarised changes made to the Capital Programme since Month 4 to the end of Month 6 (September 2017), along with expenditure to date and projected outturn.
Table 1 in the report showed how the programme had changed during 2017/18 with more detailed information relating to each Portfolio being appended to the report.
The report covered carry forward sums from 2016/17; changes during the period; capital expenditure compared to budget; carry forward into 2018/19; additional allocations; savings; and funding of 2017/18 approved schemes.
RESOLVED:
(a) That the overall report be approved; and
(b) That the carry forward adjustments set out in the report be approved.