Capital Programme Monitoring 2021/22 (Month 6)

Meeting: 16/11/2021 - Cabinet (Item 69)

69 Capital Programme Monitoring 2021/22 (Month 6) pdf icon PDF 290 KB

Additional documents:

Decision:

As detailed in the recommendations.

Minutes:

Councillor Johnson introduced the report which summarised changes made to the Capital Programme 2021/22 since it was set in December 2020 to the end of Month 6 (September 2021), along with expenditure to date and projected outturn.

 

The Capital Programme had seen a net decrease in budget of £2.174m during the period which comprised of:

 

  • Net budget increase in the programme of £2.435m (Council Fund (CF) £6.200m, Housing Revenue Account (HRA) (£3.765m))
  • Carry Forward to 2022/23, approved at Month 4 of (£4.099m) (all CF)
  • Identified savings at Month 6 of (£0.510m) (CF).

 

Actual expenditure was £37.698m.

 

Capital receipts received in the second quarter of 2021/22, along with savings identified, totalled £1.352m.  That gave a revised projected surplus in the Capital Programme at Month 6 of £4.147m (from a Month 4 funding position surplus of £2.795m) for the 2021/22 – 2023/24 Capital Programme, prior to the realisation of additional capital receipts and/or other funding sources.

 

The Corporate Finance Manager provided details of each of the tables outlined in the report.

 

RESOLVED:

 

(a)       The the report be approved;

 

(b)       That the carry forward adjustments be approved; and

 

(c)        That the additional allocations be approved.