Capital Programme Monitoring 2022/23 (Outturn)
Meeting: 18/07/2023 - Cabinet (Item 27)
27 Capital Programme Monitoring 2022/23 (Outturn) PDF 190 KB
Additional documents:
- Enc. 1 for Capital Programme Monitoring 2022/23 (Outturn), item 27 PDF 36 KB
- Enc. 2 for Capital Programme Monitoring 2022/23 (Outturn), item 27 PDF 92 KB
- Enc. 3 for Capital Programme Monitoring 2022/23 (Outturn), item 27 PDF 153 KB
- Webcast for Capital Programme Monitoring 2022/23 (Outturn)
Decision:
As detailed in the recommendations.
Minutes:
Councillor Johnson introduced the report which summarised the final outturn position for 2022/23 together with changes to the Capital Programme during the last quarter.
The Capital Programme had seen a net decrease in budget of (£12.735m) during the last quarter which comprised of:-
- Net budget decrease in the programme of (£6.382m) (See Table 2 - Council
Fund (CF) (£4.243m), Housing Revenue Account (HRA) (£2.139m);
- Carry Forward to 2023/24, approved at Month 9 of (£3.060m) partially offset
by Carry Forward reversal of £0.245m;
- Switch of School Maintenance grant (£2.524m) and Additional Learning
Needs grant (£1.001m) (all CF);
- Identified savings at outturn of (£0.013m) (CF)
Actual expenditure for the year was £55.013m.
The final outturn funding surplus from the 2022/23 – 2024/25 Capital Programme was £4.313m. The 2023/24 – 2025/26 Capital Programme was approved on the 24th January 2023, accounting for £3.376m of the current year surplus towards the programme and leaving a projected funding surplus of £0.365m. The final outturn
for 2022/23 had the impact of a revised opening funding position surplus of £1.302m, prior to the realisation of additional capital receipts and/or other funding sources.
The Democratic Services Manager explained that the report had been considered at Corporate Resources Overview and Scrutiny Committee the previous week and no comments were made.
RESOLVED:
(a) That the overall report be approved;
(b) That the carry forward adjustments be approved; and
(c) That the additional allocations be approved.