050730 - Full Application - Engineering works to provide flood defence strengthening along 1.5 km of the River Dee embankment to include sheet piling to a maximum depth below ground of 12m and a minimum height of 7.2m AOD and a proposed temporary acc

31/07/2013 - Full Application - Engineering works to provide flood defence strengthening along 1.5 km of the River Dee embankment to include sheet piling to a maximum depth below ground of 12m and a minimum height of 7.2m AOD and a proposed temporary access route

    

            That planning permission be granted subject to the conditions detailed in the report of the Head of Planning with condition 6 being amended to exclude the use of impact driving percussive piling and condition 8 being changed to require submission of a noise control scheme prior to the start of the work.

 

Councillor Patrick Heesom indicated that he wished it to be recorded in the minutes that he had abstained from voting.