Capital Programme Monitoring 2016/17 (Month 6)
The report summarises changes made to the
Capital Programme 2016/17 since Month 4 to the end of Month 6
(September 2016), along with expenditure to date and projected
outturn.
Decision type: Allweddol
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 27/10/2016
Report Type: Operational;
Decision due: 15 Nov 2016 by Cabinet
Lead member: Leader of the Council
Lead director: Corporate Finance Manager
Department: Finance
Contact: Andrew Elford Email: andrew.j.elford@flintshire.gov.uk.
Decisions
- 16/11/2016 - Capital Programme Monitoring 2016/17 (Month 6)
Agenda items
- 15/11/2016 - Cabinet Capital Programme Monitoring 2016/17 (Month 6) 15/11/2016
Documents
- Capital Programme Monitoring 2016/17 (Month 6)